The board is collecting bids to repair or replace the roads throughout Deer Point. Every quote received so far is listed here, with what it covers and what it would cost a typical household financed over ten years.

Where things stand

We are still gathering quotes. No contractor has been selected, no assessment has been approved, and every figure on this page is subject to change.

Lots assessed
61
Assumed term
10 years at 6%
Change order allowance
10%
Municipality
Oakland Township

Concrete or asphalt

The bids fall into two approaches that buy different work, so a low asphalt price and a high concrete price are not competing offers for the same job.

  • Concrete. Full reconstruction of the road surface. Higher cost, much longer service life.
  • Asphalt. A 2" resurface over the existing roads. Cheaper up front, shorter life, and recurring crack repair.

Compare bids within a group rather than across the two.

The main entrance

The Deer Point main entrance street is now Oakland Township's responsibility and sits outside this project. Hutch Paving's Option 1 is the exception, because its price includes the front entrance.

How the money would work

An approved project would go through a special assessment district and be repaid over time rather than billed at once. The per-household figures on this page spread the full cost across all 61 lots in equal annual installments.

Each lot's share is set by its frontage on the plat map, so shares differ. The smallest assessment runs about 3% below average, the largest about 14% above.

TODO: Confirm with the township whether the SAD financing terms shown here (10 years at 6%) match what would actually be offered.

What each option would cost a household

Each quote below covers the whole subdivision. Figures add a 10% change order allowance, then spread the total across 61 lots, repaid over 10 years at 6%.

OptionProject costFinancedPer home / yearPer home total
Concrete — full reconstruction
BSI Paving — entire subdivision$1,600,000$1,760,000$3,920$39,201
Al's Asphalt — entire subdivisionRough estimate, not a quote$1,970,060$2,167,066$4,827$48,268
RCOC proposal$2,423,956$2,666,352$5,939$59,389
Asphalt — 2" resurface
Hutch Paving — Option 1$251,650$276,815$617$6,166
Simon Paving — asphalt$488,200$537,020$1,196$11,961

Compare within a material rather than across. Concrete replaces the road surface and asphalt resurfaces it, so the two groups buy different work and different service lives. These per-home figures are averages: because each lot’s share is set by its frontage, individual assessments run from about 2.7% below to about 13.9% above these numbers.

Concrete quotes

Full reconstruction of the road surface. Higher cost, longer service life.

  • Formal quote

    RCOC proposal

    Concrete reconstruction under the RCOC proposal, shown net of the special assessment district contribution.

    $2,423,956.26

    The gross RCOC proposal is $3,231,941.68. A 25% SAD contribution of $807,985.42 is deducted, leaving the figure shown above.

    Additional costs not included in the total: a $300 application fee and an estimated $7,500 in other permits still to be determined.

    The SAD revision portion is expected to reduce homeowner cost by an estimated $10,000–$11,000 per lot.

  • Formal quote

    BSI Paving — entire subdivision

    8" 4500 PSI concrete, entire subdivision, including both courts and repair areas.

    $1,600,000.00

    137,000 sq ft · $11.68/sq ft

    Project 26-0761 · Dated Aug 18, 2026

    Quote is good for 15 days and requires a 30% deposit to start.

    Open question: BSI's own per-square-foot run rate works out to roughly $1,425,000 for this scope, but the quote came in at $1,600,000. The board has asked BSI to explain the difference.

    A 2027 estimate would add roughly 3% (~$15,000).

    BSI quoted these unit rates and possible adders separately:

    • Stone: $55 per ton
    • Undercutting: $55 per cubic yard
    • Permit administration: $250 flat, only if BSI pulls the permit rather than the association
    • Seed and straw: $1.50 per sq ft
    • Cancellation: $25 per day

    A lump-sum adder of $15,000 was mentioned but not confirmed, and sprinkler and irrigation repair rates were never provided.

    Contact: Jeremy Kochis · C: 248-804-0596 / O: 248-647-8373 · jeremyk@bsipaving.com

  • Rough estimate

    Al's Asphalt — entire subdivision

    8" 4000 PSI concrete across the whole subdivision, extrapolated from Al's per-square-foot pricing.

    $1,970,060.00

    137,000 sq ft · $14.38/sq ft

    Dated Jul 1, 2026

    Al's has not bid the whole subdivision. This figure applies their rate of $14.38/sq ft to 137,000 sq ft, so treat it as an order of magnitude rather than a price.

    Contact: Dana Palazzolo · 734-946-1880 / 734-431-2439 (c) · dana@alsasphalt.com

  • Formal quotePartial scope

    Al's Asphalt — courts and repair areas

    8" 4000 PSI concrete, including replacement of both courts.

    $424,365.00

    29,511 sq ft · $14.38/sq ft

    71856-2026 · Dated Jul 1, 2026

    Contact: Dana Palazzolo · 734-946-1880 / 734-431-2439 (c) · dana@alsasphalt.com

  • Formal quotePartial scope

    Al's Asphalt — patch sections

    8" 4000 PSI concrete, patch sections per the map provided.

    $311,897.00

    21,334 sq ft · $14.62/sq ft

    71834-2026 · Dated Jul 1, 2026

    Covers only the sections marked on the map given to the contractor.

    Contact: Dana Palazzolo · 734-946-1880 / 734-431-2439 (c) · dana@alsasphalt.com

  • Rough estimate

    Simon Paving — concrete

    Concrete, rough order-of-magnitude only.

    No firm figure provided

    Simon Paving gave a verbal range of $1.5 million to $2.0 million for concrete. No formal quote was provided and no square footage was specified, so there is no single figure to compare against the other bids.

Asphalt quotes

A 2-inch resurface over the existing roads. Lower cost up front, shorter life, recurring crack repair.

  • Formal quote

    Hutch Paving — Option 1

    2" asphalt resurface, 5E1 MDOT grade, entire subdivision including the front entrance (Deer Point Rd).

    $251,650.00

    122,500 sq ft · $2.05/sq ft

    BID · Dated Aug 28, 2026

    Includes mill and overlay at the curbs to leave a clean edge. October 2026 is the latest Hutch can schedule the work this year.

    A Grade #2 material upgrade is available for roughly $262,000 total, which Hutch says wears better and lasts longer.

    This option includes the front entrance, which the rest of the project treats as Oakland Township's responsibility.

    Contact: Mike Chunko · 248-514-6922 · mchunko@hutchpaving.com

  • Formal quotePartial scope

    Hutch Paving — Option 2

    2" asphalt resurface, 5E1 MDOT grade, repair sections only, plus crack and joint repair.

    $131,350.00

    42,280 sq ft · $3.11/sq ft

    BID · Dated Aug 28, 2026

    The total above combines two line items: $107,600 for the repair sections themselves (40,780 sq ft) and a $23,750 adder to crack-fill concrete and remove and patch asphalt from the township (1,500 sq ft). The quote includes 2,000 linear feet of crack and joint repair, out of roughly 25,000 linear feet total; the repair-section line covers 1,500 linear feet of joint repair.

    Estimated lifespan is 8–10 years, with maintenance crack repair needed every 3–5 years. Hutch cites Glacier Club as a reference, where comparable work has lasted 9 years.

    Contact: Mike Chunko · 248-514-6922 · mchunko@hutchpaving.com

  • Formal quote

    Simon Paving — asphalt

    2" asphalt resurface, MDOT Commercial grade, entire subdivision less the front entrance drive.

    $488,200.00

    120,000 sq ft · $4.07/sq ft

    Quote No. 8873 · Dated Aug 3, 2026

    Simon quotes a heavier commercial-grade mix than the other asphalt bids, estimates a 20-year lifespan, and says it cures fast. Carries a 1-year workmanship and materials warranty.

    Terms are 50% deposit and 50% on completion. Simon provides a golf cart to move residents around during the work. November 2026 is the latest they can schedule this year; pushing to 2027 would add 5–10%.

    Estimated ongoing maintenance is about $5,000 for crack repair every 3–5 years.

    Contact: Bob · 855-432-7302 / 734-231-0109 · simonpavingmi@gmail.com

No longer under consideration

  • Formal quotePartial scopeWithdrawn

    Allied Construction

    Repair areas only, assumed based on the pricing provided.

    $568,320.00

    Dated Aug 1, 2026

    The supporting details Allied said they would provide never arrived, so the figure could not be verified or compared against the other bids.

    Contact: Daniel Sreckovic · 248-638-0891

General conditions

Questions about the road project?

Bring them to a board meeting, or contact the board. Assessments are tentative and could change depending on the accepted low bid of whichever contractor is hired.